Who is building data centers in Texas, where, and for how much

We track 42 Texas data center projects, 25 of them building or running. The largest disclosed figure is Stargate Frontier, $25B announced (full campus); its state filings total $10.6B across 11 registered buildings. 14 of the 21 projects with a sourced power source plan on-site gas generation, alone or alongside the grid. Since August 3, 2026, ERCOT has paused energizing new data centers of 75 MW or more while the Governor's audit runs; its report is due December 10, 2026.

registered with the state (buildings only)
$35.9B
TDLR estimated construction cost, 19 projects. Not total spend.
largest announced (full campus)
$25B
Stargate Frontier. 13 projects announce a figure; scopes differ, never added.
projects tracked
42
25 building or running · 47 more state filings, listed separately
plan on-site gas
14 of 21
Of projects with a sourced power source
All projects are listed with the same facts in the table that follows the map. A text description by region is under the map.HoustonHoustonDallasAustinAustinSan AntonioSan AntonioEl PasoEl PasoAmarilloLubbockLubbockDFW, 2.4xDFWPermian, 2.2xPermianStargate Abilene expansion (+600 MW): Cancelled, Not statedDiode Ventures, Cedar Creek Lake: Cancelled, Not statedPoolside Project Horizon, Pecos County: Paused, On-site gasLancium, Fort Stockton: Record only, Not statedCrusoe, Wilbarger County: Record only, Not statedCrusoe, Howard County (Elbow Creek): Record only, Not statedCompass Datacenters, Red Oak: Record only, Not statedOracle, Bexar County: Record only, Not statedChevron and Microsoft, Project Kilby (Reeves County): Announced, On-site gasPrometheus Hyperscale and Istmo, Reeves County: Announced, On-site gasGW Ranch and Amazon, Pecos County: Announced, On-site gasPowerBridge Alpha Digital Campus, Reeves County: Announced, On-site gasNRG and LandBridge, Reeves County (potential): Announced, Grid (ERCOT)IREN Sweetwater, Nolan County: Announced, Grid (ERCOT)Texas Critical Data Centers, Odessa: Announced, On-site gasAmazon, Floydada: Announced, Not statedAmazon, Boling: Announced, Not statedCrusoe Abilene, Microsoft campus: Under construction, On-site gasStargate Frontier, Shackelford County: Under construction, On-site gasStargate Milam County: Under construction, Not statedNscale and Ionic, Ward County: Under construction, Not statedFermi America Project Matador, Carson County: Under construction, On-site gasGoogle, Armstrong County (Crusoe Goodnight): Under construction, Hybrid (grid plus on-site)Google, Haskell County: Under construction, Renewables plus storageGoogle Meitner Energy Center, Gray and Roberts Counties: Under construction, Renewables plus storageMeta, El Paso: Under construction, Hybrid (grid plus on-site)Galaxy Helios, Dickens County: Under construction, Grid (ERCOT)Cipher Barber Lake, Mitchell County: Under construction, Grid (ERCOT)TeraWulf and Fluidstack, Abernathy: Under construction, Not statedCloudBurst San Marcos GigaCenter: Under construction, On-site gasNexus Data Centers, Hubbard: Under construction, On-site gasSTACK Infrastructure, Lancaster (DFW02): Under construction, Not statedSkybox Datacenters, Hutto: Under construction, Not statedStargate Abilene: Partly operating, Hybrid (grid plus on-site)IREN Childress: Partly operating, Grid (ERCOT)Edged, Irving: Partly operating, Not statedSwitch, Round Rock: Partly operating, Not statedCompass Datacenters, Allen: Operating, Not statedCoreWeave, Plano: Operating, Not statedDigital Realty, Dallas: Operating, Not statedQTS, Fort Worth: Operating, Not statedRiot Platforms, Corsicana: Operating, Not stated
Select a marker or a table row to see its record here. Every project is also in the table below.
STATUSOperating or partlyBuildingAnnouncedPausedCancelledRecord onlySHAPE = POWERGridOn-site gasHybrid or renewablesOpen ring: not statedSIZEAnnounced $: 13 of 42 have a figure; others are small.City or county precision
Size by:
Text description of the map
Embed this map

Copy this into your page. The view links back here.

<iframe src="https://modalpoint.com/texas-data-center-map/embed" title="Texas data center map" width="100%" height="760" loading="lazy"></iframe> <p>Map: <a href="https://modalpoint.com/texas-data-center-map">ModalPoint Texas Data Center Map</a></p>

Every tracked Texas data center project

Click a row for the full record with a source for every figure. Filters change the address bar, so any view can be shared.

What do you sell?
Status
Power
Press / to search.Showing 42 of 42Loading filters...
42 tracked Texas data center projects. Data as of Oct 9, 2026.
WherePowerDollars, sort byBuilders and suppliers
NEWVantage Data Centers · for Oracle and OpenAIAlbany area (Hamby) CountyUnder constructionOn-site gas
Ann$25B campus
TDLR$10.6B 11 filed
IT1,400
Q4 2026 · P
Kiewit
3/6 evidence signals presentMedium confidence

Stargate Frontier, Shackelford County

Vantage Data Centers; tenants Oracle and OpenAI.

Who builds and supplies

Design firm
Kiewittdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 3 of 6 signals

Present: State filing (TDLR), Air permit, Confirmed groundbreaking. Not found: Local incentive record, Named contractor, Supply contract.

Status and confidence

Status, as of Dec 15, 2025
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$25B (full campus)datacenterdynamics.comFull campus (10 buildings, 1.4 GW per Vantage)
State-filed estimate (TDLR)
$10.6B across 11 registrations, buildings onlytdlr.texas.govDesign: Kiewit. Start 2025-09-26, completion 2028-05-11.
Not published
Incentive-committed
TDLR shows $10.6B for 11 Vantage buildings against $25B announced for the full campus including fit-out, power and equipment.

Megawatts: IT, generation and design are separate

IT load
1,400 MWdatacenterdynamics.com
Not published
Generation, Design capacity
1.4 GW is Vantage's critical IT figure; Epoch AI projects 2.0 GW gross.

Where, when and power

Location
Albany area (Hamby), Shackelford County (West Texas)Marker is county centroid (approximate). ~1,200 acres east of SH 351 near its intersection with FM 604, SW corner of Shackelford Co. near Hamby (~15 min from Abilene)OpenStreetMap
Groundbreaking
Dec 2025 (P: trade press)datacenterdynamics.com
First power
Q4 2026 (P: trade press)datacenterdynamics.com
Completion
May 11, 2028 (T: TDLR filing)tdlr.texas.gov
Power source
On-site gas
Water
Not published

More sources: epoch.ai

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

Crusoe · for Oracle and OpenAIAbilene CountyPartly operatingHybrid
Ann$15B JV financing
TDLR$4.49B 14 filed
Inc$3.5B
Design1,200
Q4 2026 · T
DPR ConstructionRosendinSouthland Industries+2
4/6 evidence signals presentMedium confidence

Stargate Abilene

Crusoe; developer Lancium; tenants Oracle and OpenAI.

Who builds and supplies

General contractor
DPR Constructionnewenglandconstruction.news
Electrical
Rosendinnewenglandconstruction.news
Mechanical
Southland Industriesnewenglandconstruction.news
Power EPC
Mortensonmortenson.com
Design firm
HKStdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
generation equipment, gas supply

Seller segments: Electrical and EPC

Evidence: 4 of 6 signals

Present: State filing (TDLR), Local incentive record, Named contractor, Confirmed groundbreaking. Not found: Air permit, Supply contract.

Status and confidence

Status, as of Mar 27, 2026
Partly operatingPhase 2 under construction; campus targeted at 1.2 GW by end-2026 (Crusoe).
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$15B (joint-venture financing scale)bloomberg.comJV financing scale from trade and financial press (JPMorgan loans $9.6B incl. $7.1B phase 2; about $5B equity), not a Crusoe release.
State-filed estimate (TDLR)
$4.49B across 14 registrations, buildings onlytdlr.texas.govDesign: HKS, Inc. Start 2024-06-01, completion 2026-12-21.
Incentive-committed (Inc)
$3.5B (Ch.312 abatement)businessinsider.nl'Targeted investment' under Abilene (85% for 10 years) and Taylor County (80%) abatements; qualifying minimum $2.4B; 357 jobs.

Megawatts: IT, generation and design are separate

Design capacity
1,200 MWcrusoe.ai
Not published
IT load, Generation

Where, when and power

Location
Abilene, Taylor County (West Texas)Marker is site-level. Lancium Clean Campus, far northern Abilene near Spinks Rd / Summerhill Rd; building addresses on FM 2404 (e.g. 617 FM 2404 = Lancium Buildings 5-8)OpenStreetMap
Groundbreaking
2022 (C: company statement)crusoe.ai
Completion
Dec 21, 2026 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Hybrid (grid plus on-site)
Water
Not published

More sources: epoch.ai

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWCloudBurst Data CentersSan Marcos / New Braunfels area and CountiesUnder constructionOn-site gas
Ann$14.5B campus
Incon file
Design1,200
Q4 2026 · C
Energy Transfer
3/6 evidence signals presentMedium confidence

CloudBurst San Marcos GigaCenter

CloudBurst Data Centers.

Who builds and supplies

Gas supply
Energy Transfergasprocessingnews.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment

Seller segments: Midstream gas

Evidence: 3 of 6 signals

Present: Local incentive record, Supply contract, Confirmed groundbreaking. Not found: State filing (TDLR), Air permit, Named contractor.

Status and confidence

Status, as of Nov 18, 2025
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$14.5B (full campus)datacenterdynamics.comfull 1.2 GW campus, 10-12 buildings in three 400 MW phases
Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)herald-zeitung.com
Not published
State-filed estimate

Megawatts: IT, generation and design are separate

Design capacity
1,200 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
San Marcos / New Braunfels area, Hays and Guadalupe Counties (Central Texas)Marker is site-level. 706 acres between Center Point Road, Francis Harris Lane and Huber Road, N. Guadalupe County bordering Hays CountyOpenStreetMap
Groundbreaking
Nov 2025 (C: company statement)datacenterdynamics.com
First power
Q4 2026 (C: company statement)datacenterdynamics.com
Not published
Completion
Power source
On-site gasEnergy Transfer (Oasis Pipeline, up to 450,000 MMBtu/d, subject to FID)
Water
Not published

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWMeta · for MetaEl Paso CountyUnder constructionHybrid
Ann$10B campus
TDLR$289M 1 filed
Inc$800M
Gen366
Design1,000
2028 · C
StantecEnchanted Rock
4/6 evidence signals presentHigh confidence

Meta, El Paso

Meta; tenant Meta.

Who builds and supplies

Design firm
Stantectdlr.texas.gov
Generation equipment
Enchanted Rockinsideclimatenews.org
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, gas supply

Seller segments: On-site generation

Evidence: 4 of 6 signals

Present: State filing (TDLR), Local incentive record, Supply contract, Confirmed groundbreaking. Not found: Air permit, Named contractor.

Status and confidence

Status, as of Jul 28, 2026
Under construction
Confidence
High (primary document read)

Dollars: three types, never added

Announced (Ann)
$10B (full campus)news.bgov.comFull campus, 'more than $10B' (raised from an initial $1.5B); JV total reported at $14B.
State-filed estimate (TDLR)
$289M across 1 registration, buildings onlytdlr.texas.govDesign: Stantec (Engineer of Record). Start 2025-11-01, completion 2029-02-28.
Incentive-committed (Inc)
$800M (Ch.312 abatement)elpasotexas.gov
$10B announced, $800M local minimum in the Ch.312 agreement, and $289M registered with TDLR for the first of 12 buildings (Project Seafox).

Megawatts: IT, generation and design are separate

Generation
366 MWabout.fb.com
Design capacity
1,000 MWabout.fb.com
Not published
IT load

Where, when and power

Location
El Paso, El Paso County (West Texas)Marker is site-level. ~1,039 acres on north side of Stan Roberts Sr. Ave (FM 2529), west of US 54, far NE El Paso near NM line; TDLR address 7001 Stan Roberts Sr (Project Seafox)OpenStreetMap
Groundbreaking
Oct 2025 (C: company statement)about.fb.com
First power
2028 (C: company statement)about.fb.com
Completion
Feb 28, 2029 (T: TDLR filing)tdlr.texas.gov
Power source
Hybrid (grid plus on-site)
Water
Closed-loop cooling (Meta: zero water for a majority of the year)about.fb.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWIREN · for MicrosoftChildress CountyPartly operatingGrid
Ann$5.8B GPU capex
Design750
2026 · CNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentHigh confidence

IREN Childress

IREN; tenant Microsoft.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Nov 6, 2025
Partly operating
Confidence
High (primary document read)

Dollars: three types, never added

Announced (Ann)
$5.8B (GPU capex only)sec.govGPU-related capex for the Microsoft contract (Horizon 1-4, about 200 MW IT); excludes shell and power.
Not published
State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
750 MWnasdaq.com
Not published
IT load, Generation

Where, when and power

Location
Childress, Childress County (Panhandle)Marker is city centroid (approximate). 750 MW campus on ~420 acres; listed address 620 FM 1033 Childress (tracker-listed), 345 kV ERCOT connectionOpenStreetMap
First power
2026 (C: company statement)nasdaq.com
Not published
Groundbreaking, Completion
Power source
Grid (ERCOT)
Water
Not published

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWFermi America · for TensorWaveAmarillo (site ~17 mi NE, adjacent to Pantex) CountyUnder constructionOn-site gas
Ann$2B phase
Incon file
Design11,000
No public date
PrimorisTSKSiemens Energy
5/6 evidence signals presentMedium confidence

Fermi America Project Matador, Carson County

Fermi America; tenant TensorWave.

Who builds and supplies

Power EPC
Primorissec.gov
Power EPC
TSKsec.gov
Generation equipment
Siemens Energysec.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, design firm, gas supply

Seller segments: On-site generation, Electrical and EPC

Evidence: 5 of 6 signals

Present: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking. Not found: State filing (TDLR).

Status and confidence

Status, as of Aug 13, 2026
Under constructionSite and foundation work; paused Feb 2026 pending an air permit, resumed after. First power not reported.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$2B (one phase or part of the campus)sec.govPhase 0 and Phase 1 only (company says could exceed $2B). Full buildout $70-90B across all phases is not used.
Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)newschannel10.com
Not published
State-filed estimate

Megawatts: IT, generation and design are separate

Design capacity
11,000 MWsec.gov
Not published
IT load, Generation

Where, when and power

Location
Amarillo (site ~17 mi NE, adjacent to Pantex), Carson County (Panhandle)Marker is county centroid (approximate). ~5,800-7,570 acre Texas Tech University System land (99-yr lease) adjacent to DOE Pantex Plant, Carson CountyOpenStreetMap
Groundbreaking
Oct 2025 (C: company statement)sec.gov
Not published
First power, Completion
Power source
On-site gas
Water
Not published

More sources: newschannel10.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

CoreWeave (hosted by Flexential)Plano CountyOperatingNot stated
Ann$1.6B other scope
TDLR$212M 2 filed
Inc$1.6B
Not publishedQ4 2023 · P
Critical Project Services
2/6 evidence signals presentMedium confidence

CoreWeave, Plano

CoreWeave (hosted by Flexential).

Who builds and supplies

Design firm
Critical Project Servicestdlr.texas.gov
Not yet checked
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 2 of 6 signals

Present: State filing (TDLR), Local incentive record. Not found: Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
OperatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$1.6B (scope described in the record)communityimpact.comPlano facility over 2023-2024 (company-stated equipment and improvements).
State-filed estimate (TDLR)
$212M across 2 registrations, buildings onlytdlr.texas.govOwner of record: 1000 COIT ROAD LP; Lincoln Property Company. Design: Critical Project Services. Start 2023-04-11, completion 2027-12-02.
Incentive-committed (Inc)
$1.6B (city agreement)areadevelopment.comReported as 50% of $1.6B minimum improvements rebated over 2025-2026 (search summaries only).

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Plano, Collin County (North Texas (Dallas-Fort Worth))Marker is address-level. 1000 Coit Rd, Plano; 450,000 sq ft existing buildingOpenStreetMap
Completion
Dec 31, 2023 (P: trade press)communityimpact.com
Not published
Groundbreaking, First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

NEWFluidstack-led joint venture (TeraWulf) · for FluidstackAbernathy CountyUnder constructionNot stated
Ann$1.34B other scope
IT168
2026 · CNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentHigh confidence

TeraWulf and Fluidstack, Abernathy

Fluidstack-led joint venture (TeraWulf); tenant Fluidstack.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Oct 29, 2025
Under construction
Confidence
High (primary document read)

Dollars: three types, never added

Announced (Ann)
$1.34B (scope described in the record)sec.govLow end of the company-stated $8-10M per MW critical IT x 168 MW (range $1.34B-$1.68B); construction only.
Not published
State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
Generation, Design capacity

Where, when and power

Location
Abernathy, Hale County (Panhandle)Marker is city centroid (approximate). 29.3-acre parcel in Abernathy (Hale/Lubbock counties) per TeraWulf 8-K, 120-acre campus per DCD; building >637,000 sq ft; parcel address not publishedOpenStreetMap
First power
2026 (C: company statement)datacenterdynamics.com
Not published
Groundbreaking, Completion
Power source
Not stated
Water
Not published

More sources: investors.terawulf.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWCrusoe · for GoogleClaude CountyUnder constructionHybrid
Ann$1B phase
TDLR$4.58B 10 filed
Incon file
Design530
Q3 2027 · T
DPR ConstructionRosendinSouthland Industries+2
5/6 evidence signals presentMedium confidence

Google, Armstrong County (Crusoe Goodnight)

Crusoe; tenant Google.

Who builds and supplies

General contractor
DPR Constructionnewenglandconstruction.news
Electrical
Rosendinnewenglandconstruction.news
Mechanical
Southland Industriesnewenglandconstruction.news
Design firm
Architect Orange (AO)tdlr.texas.gov
Design firm
HKStdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
Power EPC, generation equipment, gas supply

Seller segments: Electrical and EPC

Evidence: 5 of 6 signals

Present: State filing (TDLR), Local incentive record, Air permit, Named contractor, Confirmed groundbreaking. Not found: Supply contract.

Status and confidence

Status, as of Jul 31, 2026
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$1B (one phase or part of the campus)theenergymag.comTwo additional buildings only (Bldg 3 and 4, about $500M each); campus has at least six buildings and no full-campus figure.
State-filed estimate (TDLR)
$4.58B across 10 registrations, buildings onlytdlr.texas.govDesign: Architect Orange LLP dba AO; HKS Inc.. Start 2025-08-25, completion 2027-07-30.
Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)newschannel10.com

Megawatts: IT, generation and design are separate

Design capacity
530 MWtheenergymag.com
Not published
IT load, Generation

Where, when and power

Location
Claude, Armstrong County (Panhandle)Marker is city centroid (approximate). Off Lima Road just east of Hwy 207, south of Claude; ~350 acres; 3.5M sq ft originallyOpenStreetMap
Groundbreaking
Oct 2025 (P: trade press)theenergymag.com
Completion
Jul 30, 2027 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Hybrid (grid plus on-site)
Water
Not published

More sources: ksat.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

SwitchRound Rock CountyPartly operatingNot stated
Ann$250M other scope
TDLR$20M 1 filed
Inc$80M
Not publishedQ2 2028 · T
Corgan
2/6 evidence signals presentHigh confidence

Switch, Round Rock

Switch.

Who builds and supplies

Design firm
Corgantdlr.texas.gov
Not yet checked
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 2 of 6 signals

Present: State filing (TDLR), Local incentive record. Not found: Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Partly operatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
High (primary document read)

Dollars: three types, never added

Announced (Ann)
$250M (scope described in the record)roundrocktexas.govAnticipated total spend by Switch and its customers (Round Rock city summary).
State-filed estimate (TDLR)
$20M across 1 registration, buildings onlytdlr.texas.govOwner of record: Switch, Ltd. Design: Corgan Associates Inc.. Start 2026-06-01, completion 2028-06-01.
Incentive-committed (Inc)
$80M (Ch.380 agreement)roundrocktexas.govRound Rock Ch.380 agreement approved 7-0 on 2022-12-15: minimum $80M by end of 2026, 50% of the city sales tax back through 2037.

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Round Rock, Williamson County (Central Texas)Marker is site-level. 'The Rock' campus east of S Mays St, north of Dell Way (land bought from Dell); 150 Dell Way per briefOpenStreetMap
Groundbreaking
Q3 2026 (P: trade press)roundrocktexas.gov
Completion
Jun 1, 2028 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

Digital RealtyDallas CountyOperatingNot stated
Ann$104M other scope
Inc$104M
Not publishedNo public dateNot yet checked1/6 evidence signals presentMedium confidence

Digital Realty, Dallas

Digital Realty.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
OperatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$104M (scope described in the record)bisnow.comCapital improvements committed under the 2021 City of Dallas agreement. A June 2025 request asked to cut this to about $13M; outcome unverified.
Incentive-committed (Inc)
$104M (Ch.380 agreement)bisnow.comCommitment of $104M under the Dallas agreement; June 2025 request to reduce to about $13M, outcome unverified.
Not published
State-filed estimate
A June 2025 request asked Dallas to cut the $104M commitment to about $13M; the outcome is unverified.

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Dallas, Dallas County (North Texas (Dallas-Fort Worth))Marker is address-level. DFW10, 2323 Bryan St, Dallas (454,000 sq ft)OpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

Cipher Digital · for FluidstackColorado City CountyUnder constructionGrid
Inc$3.3B
Design300
Q3 2026 · PNot publicly named (checked Oct 9, 2026)1/6 evidence signals presentMedium confidence

Cipher Barber Lake, Mitchell County

Cipher Digital; tenant Fluidstack.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Nov 21, 2025
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Incentive-committed (Inc)
$3.3B (Ch.312 abatement)co.mitchell.tx.usMitchell County hearing notice dated 2026-07-23: Phase II $1.3B plus Phase III $2.0B. Outcome of the 2026-08-24 hearing and the Phase I amount were not verified.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Design capacity
300 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Colorado City, Mitchell County (West Texas)Marker is city centroid (approximate). North of I-20 near Colorado City; listed address 951 County Road 204 (aggregator-listed); ~250 acres; Cipher Barber Lake Reinvestment ZoneOpenStreetMap
First power
Q3 2026 (P: trade press)datacenterdynamics.com
Completion
Jan 2027 (P: trade press)datacenterdynamics.com
Not published
Groundbreaking
Power source
Grid (ERCOT)
Water
Not published

More sources: investors.cipherdigital.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

Compass DatacentersAllen CountyOperatingNot stated
Incon file
Not publishedNo public dateNot yet checked1/6 evidence signals presentMedium confidence

Compass Datacenters, Allen

Compass Datacenters.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
OperatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)comptroller.texas.govComptroller Ch.312: executed 2016-11-15, 50% abated, expires 2027-12-31; investment amount not disclosed.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Allen, Collin County (North Texas (Dallas-Fort Worth))Marker is address-level. 820 Allen Commerce Pkwy, Allen (City of Allen Compass Datacenters Reinvestment Zone #33, 96.66 ac)OpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

NEWCrusoe · for MicrosoftAbilene CountyUnder constructionOn-site gasNo figure published
Design900
2027 · C
Energy Transfer
2/6 evidence signals presentHigh confidence

Crusoe Abilene, Microsoft campus

Crusoe; tenant Microsoft.

Who builds and supplies

Gas supply
Energy Transferenergytransfer.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment

Seller segments: Midstream gas

Evidence: 2 of 6 signals

Present: Air permit, Supply contract. Not found: State filing (TDLR), Local incentive record, Named contractor, Confirmed groundbreaking.

Status and confidence

Status, as of Mar 27, 2026
Under construction
Confidence
High (primary document read)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
900 MWcrusoe.ai
Not published
IT load, Generation

Where, when and power

Location
Abilene, Taylor County (West Texas)Marker is site-level. Adjacent to existing Crusoe campus; TCEQ notice describes 'Longhorn Data Center' Bldgs 9 and 10, 615 FM 2404, AbileneOpenStreetMap
Groundbreaking
Mar 2026 (C: company statement)crusoe.ai
First power
2027 (C: company statement)crusoe.ai
Not published
Completion
Power source
On-site gasEnergy Transfer (agreement to build facilities supporting ~900 MW of capacity; signed Q2 2026)
Water
Not published

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

Edged EnergyIrving CountyPartly operatingNot stated
TDLR$178M 1 filed
IT48
Q1 2025 · C
MG2ThermalWorks
2/6 evidence signals presentMedium confidence

Edged, Irving

Edged Energy.

Who builds and supplies

Design firm
MG2tdlr.texas.gov
Mechanical
ThermalWorkstdlr.texas.gov
Not yet checked
general contractor, electrical, Power EPC, generation equipment, gas supply

Evidence: 2 of 6 signals

Present: State filing (TDLR), Named contractor. Not found: Local incentive record, Air permit, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Partly operatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$178M across 1 registration, buildings onlytdlr.texas.govDesign: MG2. Start 2026-07-16, completion 2028-03-27.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

IT load
48 MWrejournals.com
Not published
Generation, Design capacity

Where, when and power

Location
Irving, Dallas County (North Texas (Dallas-Fort Worth))Marker is address-level. 505 N Wildwood Dr, Irving (DFW01); second 24 MW building plannedOpenStreetMap
Groundbreaking
Jul 16, 2026 (T: TDLR filing)tdlr.texas.gov
First power
Jan 2025 (C: company statement)rejournals.com
Completion
Mar 27, 2028 (T: TDLR filing)tdlr.texas.gov
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

NEWGalaxy Digital · for CoreWeaveAfton / Spur area CountyUnder constructionGrid
TDLR$4.3B 4 filed
Design1,600
Q4 2027 · T
StantecSTG Design
1/6 evidence signals presentHigh confidence

Galaxy Helios, Dickens County

Galaxy Digital; tenant CoreWeave.

Who builds and supplies

Design firm
Stantectdlr.texas.gov
Design firm
STG Designtdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jan 16, 2026
Under constructionTrade press reports 133 MW delivered to CoreWeave in mid-2026; not independently verified here, so status not upgraded.
Confidence
High (primary document read)

Dollars: three types, never added

State-filed estimate (TDLR)
$4.3B across 4 registrations, buildings onlytdlr.texas.govDesign: STG Design; Stantec Architecture, Inc.. Start 2025-03-30, completion 2027-11-29.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
1,600 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Afton / Spur area, Dickens County (West Texas)Marker is site-level. 1,500-acre campus; TDLR addresses 984 County Road 112 (Helios 1) and 1003 FM 193 (Helios 2-4), Afton TX 79220OpenStreetMap
Groundbreaking
Mar 13, 2026 (T: TDLR filing)tdlr.texas.gov
Completion
Nov 29, 2027 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Grid (ERCOT)
Water
Not published

More sources: datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWGoogle and Intersect · for GoogleLow confidencePampa area and CountiesUnder constructionRenewables plus storage
TDLR$1.2B 3 filed
Gen1,000
Q2 2028 · T
HDR Engineering
1/6 evidence signals presentLow confidence

Google Meitner Energy Center, Gray and Roberts Counties

Google and Intersect; tenant Google.

Who builds and supplies

Design firm
HDR Engineeringtdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jun 4, 2026
Under construction
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

State-filed estimate (TDLR)
$1.2B across 3 registrations, buildings onlytdlr.texas.govDesign: HDR Engineering Inc.. Start 2025-12-19, completion 2028-04-18.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Generation
1,000 MWpowermag.com
Not published
IT load, Design capacity

Where, when and power

Location
Pampa area, Gray and Roberts Counties (Panhandle)Marker is city centroid (approximate). Four data center buildings (up to 840 MW) near Pampa in Gray County; generation in Gray and Roberts counties; 800-acre workforce hub in Wheeler CountyOpenStreetMap
Groundbreaking
Dec 19, 2025 (T: TDLR filing)tdlr.texas.gov
Completion
Apr 18, 2028 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Renewables plus storage
Water
Not published

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWGoogle · for GoogleHaskell CountyUnder constructionRenewables plus storage
TDLR$800M 2 filed
Inc$1B
Not publishedQ2 2026 · C
HDR Engineering
2/6 evidence signals presentMedium confidence

Google, Haskell County

Google; tenant Google.

Who builds and supplies

Design firm
HDR Engineeringtdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 2 of 6 signals

Present: State filing (TDLR), Local incentive record. Not found: Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jun 4, 2026
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$800M across 2 registrations, buildings onlytdlr.texas.govDesign: HDR Engineering, Inc. Start 2026-04-01, completion 2027-10-27.
Incentive-committed (Inc)
$1B (Ch.312 abatement)haskellcountytx.govHaskell County Ch.312 'Journey RZ 2025' cites about $1B for Phase 1. Crusoe's separate Haskell abatement is a different deal.
Not published
Announced
TDLR $800M for Journey 1A and 2A; the county cites about $1B for Phase 1; the separate THM1A/2A site ($700M, same owner) is listed under state filings.Google's statewide $40B Texas pledge through 2027 includes this site but is not a site figure and is not stored.

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Haskell, Haskell County (West Texas)Marker is city centroid (approximate). 1362 Red Creek Road, Haskell TX; ~300 acres; Journey 1A (285,280 sq ft) and Journey 2A (210,420 sq ft); Quantum solar/storage co-locatedOpenStreetMap
Groundbreaking
Apr 1, 2026 (T: TDLR filing)tdlr.texas.gov
First power
Jun 2026 (C: company statement)datacenters.google
Completion
Oct 27, 2027 (T: TDLR filing)tdlr.texas.gov
Power source
Renewables plus storage
Water
Not published

More sources: powermag.comhaskellcountytx.gov

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWNexus Data CentersHubbard CountyUnder constructionOn-site gas
TDLR$800M 2 filed
Design612
Q4 2026 · C
Energy TransferHDR EngineeringAirJoule
3/6 evidence signals presentMedium confidence

Nexus Data Centers, Hubbard

Nexus Data Centers.

Who builds and supplies

Gas supply
Energy Transferenergytransfer.com
Design firm
HDR Engineeringtdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment

Seller segments: Midstream gas, Water

Evidence: 3 of 6 signals

Present: State filing (TDLR), Air permit, Supply contract. Not found: Local incentive record, Named contractor, Confirmed groundbreaking.

Status and confidence

Status, as of Aug 4, 2026
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$800M across 2 registrations, buildings onlytdlr.texas.govDesign: HDR Engineering, Inc. Start 2026-01-06, completion 2028-01-05.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
612 MWenergytransfer.com
Not published
IT load, Generation

Where, when and power

Location
Hubbard, Hill County (Central Texas)Marker is site-level. 357 HCR 3372, Hubbard TX (TDLR); ~2,900-3,000 acre campus off Highway 171 outside Hubbard city limitsOpenStreetMap
Groundbreaking
Jan 6, 2026 (T: TDLR filing)tdlr.texas.gov
First power
Q4 2026 (C: company statement)energytransfer.com
Completion
Jan 5, 2028 (T: TDLR filing)tdlr.texas.gov
Power source
On-site gasEnergy Transfer (firm transportation, initial ~150 MMcf/d, Q4 2026)
Water
AirJoule atmospheric water harvesting from waste heat (proposed purchase agreement, deployment 2H 2026)energytransfer.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWIonic Digital (landlord) and Nscale · for MicrosoftBarstow CountyUnder constructionNot statedNo figure published
Design234
No public dateNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentMedium confidence

Nscale and Ionic, Ward County

Ionic Digital (landlord) and Nscale; tenant Microsoft.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Oct 15, 2025
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
234 MWbackend.theenergymag.com
Not published
IT load, Generation

Where, when and power

Location
Barstow, Ward County (Permian Basin)Marker is city centroid (approximate). Owned 234 MW facility, Barstow area; aggregator-listed address 3013 FM 516 Barstow; ~700 MW potentialOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

More sources: SEC

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

QTSLow confidenceFort Worth CountyOperatingNot stated
TDLR$472M 3 filed
Not publishedQ4 2027 · T
Corgan
1/6 evidence signals presentLow confidence

QTS, Fort Worth

QTS.

Who builds and supplies

Design firm
Corgantdlr.texas.gov
Not yet checked
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
OperatingCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

State-filed estimate (TDLR)
$472M across 3 registrations, buildings onlytdlr.texas.govOwner of record: Quality Technology Services, LLC; Quality Technology Services (QTS). Design: Corgan Associates Inc.. Start 2025-07-01, completion 2027-10-01.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Fort Worth, Tarrant County (North Texas (Dallas-Fort Worth))Marker is address-level. 14100 Park Vista Blvd, Fort Worth; existing 26-ac campus plus 27 ac adjacent landOpenStreetMap
Groundbreaking
Jul 1, 2025 (T: TDLR filing)tdlr.texas.gov
Completion
Oct 1, 2027 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

Riot PlatformsLow confidenceCorsicana CountyOperatingNot stated
TDLR$400M 1 filed
Not publishedQ2 2028 · TNot yet checked1/6 evidence signals presentLow confidence

Riot Platforms, Corsicana

Riot Platforms.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
OperatingBitcoin mining site. AI conversion under evaluation; Phase II (600 MW) halted January 2025 (Riot press release, 2025-01-21).
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

State-filed estimate (TDLR)
$400M across 1 registration, buildings onlytdlr.texas.govOwner of record: Riot Platforms, Inc.. Design: Not listed. Start 2026-04-27, completion 2028-05-19.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Corsicana, Navarro County (North Texas (Dallas-Fort Worth))Marker is city centroid (approximate). Corsicana Facility, 1 GW approved capacity (~400 MW bitcoin mining; ~600 MW under AI/HPC evaluation)OpenStreetMap
Groundbreaking
Apr 27, 2026 (T: TDLR filing)tdlr.texas.gov
Completion
May 19, 2028 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

Skybox DatacentersLow confidenceHutto CountyUnder constructionNot stated
TDLR$1.15B 3 filed
Incon file
Not publishedQ4 2028 · T
Corgan
2/6 evidence signals presentLow confidence

Skybox Datacenters, Hutto

Skybox Datacenters.

Who builds and supplies

Design firm
Corgantdlr.texas.gov
Not yet checked
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 2 of 6 signals

Present: State filing (TDLR), Local incentive record. Not found: Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Under constructionCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

State-filed estimate (TDLR)
$1.15B across 3 registrations, buildings onlytdlr.texas.govOwner of record: Hutto Data Center Campus, LLC. Design: Corgan Associates, Inc.; Corgan. Start 2025-10-01, completion 2028-10-30.
Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)communityimpact.com
Not published
Announced

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Hutto, Williamson County (Central Texas)Marker is address-level. 3399 County Road 132, Hutto (Hutto 4: 846,300 sq ft); PowerCampus Austin ~150 ac, 600 MWOpenStreetMap
Groundbreaking
Oct 1, 2025 (T: TDLR filing)tdlr.texas.gov
Completion
Oct 30, 2028 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

STACK InfrastructureLancaster CountyUnder constructionNot stated
TDLR$822M 3 filed
Not published2026 · P
Corgan
1/6 evidence signals presentMedium confidence

STACK Infrastructure, Lancaster (DFW02)

STACK Infrastructure.

Who builds and supplies

Design firm
Corgantdlr.texas.gov
Not yet checked
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Under constructionCarried over from the previous version of this page; status proposed from the record and awaiting confirmation.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$822M across 3 registrations, buildings onlytdlr.texas.govOwner of record: SI DFW02A, LLC; SI DFW02CAMPUS LLC. Design: Corgan; Corgan Associates. Start 2025-05-21, completion 2028-12-14.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Lancaster, Dallas County (North Texas (Dallas-Fort Worth))Marker is address-level. DFW02A, 1000 E Belt Line Rd, Lancaster (DFW02 campus 102 ac, 6 buildings, 216 MW)OpenStreetMap
Groundbreaking
May 21, 2025 (T: TDLR filing)tdlr.texas.gov
First power
2026 (P: trade press)
Completion
Dec 14, 2028 (T: TDLR filing)tdlr.texas.gov
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

NEWSB Energy · for OpenAIMilam CountyUnder constructionNot stated
TDLR$470M 1 filed
Design1,200
Q4 2026 · P
Corgan
1/6 evidence signals presentMedium confidence

Stargate Milam County

SB Energy; tenant OpenAI.

Who builds and supplies

Design firm
Corgantdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jan 12, 2026
Under construction
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$470M across 1 registration, buildings onlytdlr.texas.govDesign: Corgan Architects Inc. Start 2025-10-20, completion 2026-10-15.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
1,200 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Milam County (Central Texas)Marker is county centroid (approximate). Milam County, ~70 miles NE of Austin; exact site not published in sources foundOpenStreetMap
First power
Oct 2026 (P: analyst (Epoch AI))datacenterdynamics.com
Completion
Q4 2028 (P: analyst (Epoch AI))datacenterdynamics.com
Not published
Groundbreaking
Power source
Not stated
Water
Not published

More sources: epoch.aiopenai.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWChevron (power) and Microsoft (campus) · for MicrosoftPecos area CountyAnnouncedOn-site gas
Ann$9B power only
IT2,000
Gen2,670
2028 · C
ChevronGE VernovaSolar Turbines (Caterpillar)+1
2/6 evidence signals presentMedium confidence

Chevron and Microsoft, Project Kilby (Reeves County)

Chevron (power) and Microsoft (campus); tenant Microsoft.

Who builds and supplies

Gas supply
Chevronchevron.com
Generation equipment
GE Vernovachevron.com
Generation equipment
Solar Turbines (Caterpillar)chevron.com
Water
Texas Pacific Landtexaspacific.com
Land
Texas Pacific Landtexaspacific.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm

Seller segments: Midstream gas, On-site generation, Water, Land

Evidence: 2 of 6 signals

Present: Air permit, Supply contract. Not found: State filing (TDLR), Local incentive record, Named contractor, Confirmed groundbreaking.

Status and confidence

Status, as of Jun 22, 2026
AnnouncedFID expected by end-2026; first power 2028 (Chevron release, 2026-06-22).
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Announced (Ann)
$9B (power plant only)globaldatacenterhub.comPower plant only (2.67 GW), analyst estimate; range $7-9B (Bloomberg earlier, TD Securities about $9B). Microsoft campus capex not disclosed.
Not published
State-filed estimate, Incentive-committed
$9B is the power plant only, an analyst estimate; the Microsoft campus cost is not disclosed.

Megawatts: IT, generation and design are separate

IT load
2,000 MWchevron.com
Generation
2,670 MWchevron.com
Not published
Design capacity

Where, when and power

Location
Pecos area, Reeves County (Permian Basin)Marker is city centroid (approximate). 2,000+ acres in Reeves County near Pecos; exact parcel not publishedOpenStreetMap
First power
2028 (C: company statement)chevron.com
Not published
Groundbreaking, Completion
Power source
On-site gasChevron (Permian natural gas, per Chevron release)
Water
Non-potable brackish groundwater (TPL has exclusive right to source aquifer water for the plant); Chevron working on produced-water reusechevron.com

More sources: orrick.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWAmazon Data Services · for AmazonBoling CountyAnnouncedNot stated
TDLR$3B 10 filed
Not publishedQ3 2027 · T
Gensler
1/6 evidence signals presentMedium confidence

Amazon, Boling

Amazon Data Services; tenant Amazon.

Who builds and supplies

Design firm
Genslertdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Aug 7, 2026
Announced
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$3B across 10 registrations, buildings onlytdlr.texas.govDesign: M. ARTHUR GENSLER & ASSOCIATES, INC.. Start 2026-08-01, completion 2027-09-01.
Not published
Announced, Incentive-committed
$3B is registered for 10 buildings; the whole-campus $10-12B in press is unverified.

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Boling, Wharton County (Houston area)Marker is city centroid (approximate). ~2,700-3,000 acres near FM 1301 and FM 442, Eaglewood Road/Drive addresses (230-270 Eaglewood), Boling TX 77420OpenStreetMap
Groundbreaking
Aug 1, 2026 (T: TDLR filing)tdlr.texas.gov
Completion
Sep 1, 2027 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

More sources: datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWAmazon Data Services · for AmazonFloydada CountyAnnouncedNot stated
TDLR$1.2B 4 filed
Not publishedQ2 2027 · T
Gensler
1/6 evidence signals presentHigh confidence

Amazon, Floydada

Amazon Data Services; tenant Amazon.

Who builds and supplies

Design firm
Genslertdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: State filing (TDLR). Not found: Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Aug 7, 2026
Announced
Confidence
High (primary document read)

Dollars: three types, never added

State-filed estimate (TDLR)
$1.2B across 4 registrations, buildings onlytdlr.texas.govDesign: M. ARTHUR GENSLER & ASSOCIATES, INC.. Start 2026-08-01, completion 2027-04-01.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Floydada, Floyd County (Panhandle)Marker is city centroid (approximate). TDLR address 1762 County Road 241, Floydada TX 79235 (Bldg B); other buildings 1750/1768/1774/1782 CR 241OpenStreetMap
Groundbreaking
Aug 1, 2026 (T: TDLR filing)tdlr.texas.gov
Completion
Apr 1, 2027 (T: TDLR filing)tdlr.texas.gov
Not published
First power
Power source
Not stated
Water
Not published

More sources: datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWAmazon Data Services · for AmazonFort Stockton / Pecos area CountyAnnouncedOn-site gas
TDLR$900M 3 filed
Gen7,650
Q4 2026 · T
Gensler
2/6 evidence signals presentMedium confidence

GW Ranch and Amazon, Pecos County

Amazon Data Services; developer Pacifico Energy; tenant Amazon.

Who builds and supplies

Design firm
Genslertdlr.texas.gov
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, generation equipment, gas supply

Seller segments: Water

Evidence: 2 of 6 signals

Present: State filing (TDLR), Air permit. Not found: Local incentive record, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Aug 10, 2026
Announced
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

State-filed estimate (TDLR)
$900M across 3 registrations, buildings onlytdlr.texas.govDesign: M. ARTHUR GENSLER & ASSOCIATES, INC.. Start 2026-08-01, completion 2026-12-01.
Not published
Announced, Incentive-committed

Megawatts: IT, generation and design are separate

Generation
7,650 MWdatacenterdynamics.com
Not published
IT load, Design capacity

Where, when and power

Location
Fort Stockton / Pecos area, Pecos County (Permian Basin)Marker is city centroid (approximate). 8,000+ acre site ~17 miles north of Fort Stockton, Pecos County (TX-18 corridor)OpenStreetMap
Groundbreaking
Aug 1, 2026 (T: TDLR filing)tdlr.texas.gov
First power
2027 (C: company statement)datacenterdynamics.com
Completion
Dec 1, 2026 (T: TDLR filing)tdlr.texas.gov
Power source
On-site gasMultiple gas connections including 15-mile pipeline to Waha hub
Water
Amazon says non-potable water unsuitable for drinking/irrigation; exploring produced waterdatacenterdynamics.com

More sources: datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWIRENSweetwater CountyAnnouncedGridNo figure published
Design2,000
Q2 2026 · CNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentMedium confidence

IREN Sweetwater, Nolan County

IREN.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Mar 17, 2025
AnnouncedSweetwater 1 was energized on 2026-05-01 (grid connection, 1.4 GW substation); whether the data center itself is operating is not confirmed. Sweetwater 2 (600 MW) targets 2027-2028.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
2,000 MWsec.gov
Not published
IT load, Generation

Where, when and power

Location
Sweetwater, Nolan County (West Texas)Marker is city centroid (approximate). Sweetwater 1: ~1,300 acres, listed address 883 FM 611 Sweetwater (tracker-listed, not company-confirmed); Sweetwater 2: ~500 acres near Hamlin/FM 540OpenStreetMap
First power
May 1, 2026 (C: company statement)sec.gov
Not published
Groundbreaking, Completion
Power source
Grid (ERCOT)
Water
Not published

More sources: nasdaq.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWNRG EnergyReeves CountyAnnouncedGridNo figure published
Gen1,100
Q4 2029 · C
LandBridge
1/6 evidence signals presentHigh confidence

NRG and LandBridge, Reeves County (potential)

NRG Energy; developer LandBridge.

Who builds and supplies

Land
LandBridges206.q4cdn.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Seller segments: Land

Evidence: 1 of 6 signals

Present: Air permit. Not found: State filing (TDLR), Local incentive record, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Sep 23, 2025
AnnouncedBuilt only if a power purchase agreement is signed. Shown as a potential site, not a firm project.
Confidence
High (primary document read)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Generation
1,100 MWs206.q4cdn.com
Not published
IT load, Design capacity

Where, when and power

Location
Reeves County (Permian Basin)Marker is county centroid (approximate). LandBridge surface acreage adjacent to Waha hub, Reeves County (Delaware Basin); parcel not publishedOpenStreetMap
First power
Q4 2029 (C: company statement)s206.q4cdn.com
Not published
Groundbreaking, Completion
Power source
Grid (ERCOT)
Water
Not published

More sources: businesswire.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWPowerBridge (Liberty Energy joint venture)Reeves CountyAnnouncedOn-site gasNo figure published
Gen2,000
Q4 2027 · C
Liberty EnergyLandBridge
1/6 evidence signals presentHigh confidence

PowerBridge Alpha Digital Campus, Reeves County

PowerBridge (Liberty Energy joint venture).

Who builds and supplies

Generation equipment
Liberty Energyinvestors.libertyenergy.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, gas supply

Seller segments: On-site generation, Land, Oilfield pivots

Evidence: 1 of 6 signals

Present: Supply contract. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Confirmed groundbreaking.

Status and confidence

Status, as of Jul 22, 2026
Announced
Confidence
High (primary document read)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Generation
2,000 MWinvestors.libertyenergy.com
Not published
IT load, Design capacity

Where, when and power

Location
Reeves County (Permian Basin)Marker is county centroid (approximate). Option to lease ~3,400 acres of LandBridge land in Reeves County near Waha gas hub; parcel not publishedOpenStreetMap
First power
Q4 2027 (C: company statement)investors.libertyenergy.com
Completion
2028 (C: company statement)investors.libertyenergy.com
Not published
Groundbreaking
Power source
On-site gas
Water
Not published

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWPrometheus HyperscaleLow confidencePecos CountyAnnouncedOn-site gasNo figure published
Design2,500
2027 · C
Istmo Midstream
1/6 evidence signals presentLow confidence

Prometheus Hyperscale and Istmo, Reeves County

Prometheus Hyperscale.

Who builds and supplies

Gas supply
Istmo Midstreamdatacenterdynamics.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment

Seller segments: Midstream gas

Evidence: 1 of 6 signals

Present: Supply contract. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Confirmed groundbreaking.

Status and confidence

Status, as of Aug 21, 2026
Announced
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
2,500 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Pecos, Reeves County (Permian Basin)Marker is city centroid (approximate). Pecos, Reeves County; co-located with Istmo Midstream fractionation facility; parcel not publishedOpenStreetMap
First power
2027 (C: company statement)datacenterdynamics.com
Not published
Groundbreaking, Completion
Power source
On-site gasPiped natural gas plus ethane from Istmo Midstream's co-located fractionation facility
Water
Closed-loop cooling (no source stated)datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWTexas Critical Data Centers (New Era Energy & Digital)Low confidenceOdessa CountyAnnouncedOn-site gasNo figure published
Design250
Q3 2027 · CNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentLow confidence

Texas Critical Data Centers, Odessa

Texas Critical Data Centers (New Era Energy & Digital).

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jul 30, 2025
Announced
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
250 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Odessa, Ector County (Permian Basin)Marker is city centroid (approximate). 438 acres (235 + 203) adjacent to Vistra's 1.1 GW gas plant in Odessa; GROW Odessa land; exact parcel not publishedOpenStreetMap
First power
Q3 2027 (C: company statement)datacenterdynamics.com
Not published
Groundbreaking, Completion
Power source
On-site gas
Water
Municipal services via proposed Industrial District with City of Odessadatacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

Compass DatacentersLow confidenceRed Oak CountyRecord onlyNot stated
Ann$300M other scope
Inc$300M
Not published2026 · PNot yet checked1/6 evidence signals presentLow confidence

Compass Datacenters, Red Oak

Compass Datacenters.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Record onlyListed in a county or state record; the current build state is not confirmed.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Announced (Ann)
$300M (scope described in the record)datacenterdynamics.comThree buildings of about 251,815 sq ft each; reported construction cost estimate.
Incentive-committed (Inc)
$300M (Ch.312 abatement)elliscountytx.govEllis County 2023-10-03 agenda, 'approximately $300+ million' (from a search summary; PDF not machine-readable). County documents are Ch.312; an earlier tracker listed Ch.380/381. Compass later withdrew an abatement request; timing unverified.
Not published
State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Red Oak, Ellis County (North Texas (Dallas-Fort Worth))Marker is city centroid (approximate). Red Oak campus; ~192.328 ac Reinvestment Zone 11 and ~12.998 ac Zone 10 (2023 agenda); reported buildings at 500/540/581 Austin BlvdOpenStreetMap
Completion
2026 (P: trade press)datacenterdynamics.com
Not published
Groundbreaking, First power
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

CrusoeLow confidenceBig Spring (Elbow Creek area, south of town) CountyRecord onlyNot stated
Incon file
Not publishedNo public dateNot yet checked1/6 evidence signals presentLow confidence

Crusoe, Howard County (Elbow Creek)

Crusoe.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Record onlyListed in a county or state record; the current build state is not confirmed.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.381 agreement)kbst.comHoward County signed a Ch.381 agreement with Crusoe in 2023; the county is reviewing it. A county judge quoted up to $110M at 'Elbow Creek' but the attribution to Crusoe is unconfirmed, so no value is stored.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Big Spring (Elbow Creek area, south of town), Howard County (Permian Basin)Marker is city centroid (approximate). Elbow Creek area south of Big Spring; modular pod-style data centerOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

CrusoeLow confidenceVernon area CountyRecord onlyNot stated
Incon file
Not publishedNo public dateNot yet checked1/6 evidence signals presentLow confidence

Crusoe, Wilbarger County

Crusoe.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Record onlyListed in a county or state record; the current build state is not confirmed.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.312 abatement)comptroller.texas.govComptroller Ch.312 report: executed 2022-11-28, 1% abated years 1-5; investment shown as $0 or blank.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Vernon area, Wilbarger County (West Texas)Marker is county centroid (approximate). Crusoe Data Center Project reinvestment zone, 320 acres, Wilbarger County (exact site not located)OpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

LanciumLow confidenceFort Stockton CountyRecord onlyNot stated
Incon file
Not publishedNo public dateNot yet checked1/6 evidence signals presentLow confidence

Lancium, Fort Stockton

Lancium.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Record onlyListed in a county or state record; the current build state is not confirmed.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.381 agreement)fortstocktonpioneer.comPecos County Ch.381 agreement from September 2021. The $30M figure is amount already invested, not a commitment, so no value is stored.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Fort Stockton, Pecos County (Permian Basin)Marker is city centroid (approximate). Clean Campus, ~110 acres NW of Fort Stockton off Pecos Highway; 325 MWOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

OracleLow confidenceSan Antonio area CountyRecord onlyNot stated
Incon file
Not publishedNo public dateNot yet checked1/6 evidence signals presentLow confidence

Oracle, Bexar County

Oracle.

Who builds and supplies

Not yet checked
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 1 of 6 signals

Present: Local incentive record. Not found: State filing (TDLR), Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status
Record onlyListed in a county or state record; the current build state is not confirmed.
Confidence
Low (single trade report or unverified)

Dollars: three types, never added

Incentive-committed (Inc)
Abatement on file, no investment figure (Ch.381 agreement)bexar.orgNo Bexar County Ch.381 agreement naming Oracle was found; the Comptroller database entry needs a direct pull.
Not published
Announced, State-filed estimate

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
San Antonio area, Bexar County (South Texas)Marker is county centroid (approximate). Not identifiedOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

· Last verified Oct 9, 2026; contractors, suppliers and power not yet checked. Data as of Oct 9, 2026.

NEWPoolsideFort Stockton area CountyPausedCoreWeave anchor lease terminated April 2026; project paused and seeking a partner (DCD citing the Financial Times, not a company statement)..On-site gasNo figure published
Design2,000
2027 · P
Longfellow Ranch
0/6 evidence signals presentMedium confidence

Poolside Project Horizon, Pecos County

Poolside.

Who builds and supplies

Land
Longfellow Ranchdatacenterdynamics.com
Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Seller segments: Land

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Apr 2, 2026
PausedCoreWeave anchor lease terminated April 2026; project paused and seeking a partner (DCD citing the Financial Times, not a company statement).
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
2,000 MWdatacenterdynamics.com
Not published
IT load, Generation

Where, when and power

Location
Fort Stockton area, Pecos County (Permian Basin)Marker is city centroid (approximate). 568 acres on Mitchell family Longfellow Ranch near Fort Stockton, Pecos CountyOpenStreetMap
Groundbreaking
Mar 2026 (P: trade press)datacenterdynamics.com
First power
2027 (P: trade press)datacenterdynamics.com
Not published
Completion
Power source
On-site gas
Water
Not published

More sources: datacenterdynamics.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWDiode VenturesCedar Creek Lake area CountyCancelledDeveloper told county officials it would not pursue the site after local opposition and the Governor's June 2026 data center standards..Not statedNo figure publishedNot publishedNo public dateNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentMedium confidence

Diode Ventures, Cedar Creek Lake

Diode Ventures.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Jul 23, 2026
CancelledDeveloper told county officials it would not pursue the site after local opposition and the Governor's June 2026 data center standards.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Not published
IT load, Generation, Design capacity

Where, when and power

Location
Cedar Creek Lake area, Henderson County (Other)Marker is county centroid (approximate). Site near Cedar Creek Reservoir inside a residential subdivision; parcel not publishedOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

More sources: argusmedia.comnewschannel6now.com

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

NEWCrusoeAbilene CountyCancelledEpoch AI: OpenAI reversed course and directed capacity elsewhere; Microsoft then took the adjacent 900 MW.Not statedNo figure published
Design600
No public dateNot publicly named (checked Oct 9, 2026)0/6 evidence signals presentMedium confidence

Stargate Abilene expansion (+600 MW)

Crusoe.

Who builds and supplies

Not publicly named (checked Oct 9, 2026)
general contractor, electrical, mechanical, Power EPC, design firm, generation equipment, gas supply

Evidence: 0 of 6 signals

Present: none. Not found: State filing (TDLR), Local incentive record, Air permit, Named contractor, Supply contract, Confirmed groundbreaking.

Status and confidence

Status, as of Mar 24, 2026
CancelledEpoch AI: OpenAI reversed course and directed capacity elsewhere; Microsoft then took the adjacent 900 MW. Oracle disputes 'cancellation' reporting. Treated as dropped for OpenAI and Oracle, replaced by Microsoft.
Confidence
Medium (one primary source read secondhand, or two secondary sources)

Dollars: three types, never added

Not published
Announced, State-filed estimate, Incentive-committed

Megawatts: IT, generation and design are separate

Design capacity
600 MWepoch.ai
Not published
IT load, Generation

Where, when and power

Location
Abilene, Taylor County (West Texas)Marker is site-level. Land adjacent to Lancium Clean Campus / Stargate Abilene (Crusoe), north of AbileneOpenStreetMap
Not published
Groundbreaking, First power, Completion
Power source
Not stated
Water
Not published

More sources: crusoe.ai

· Last verified Oct 9, 2026. Data as of Oct 9, 2026.

Dollars. Ann = announced by the company or in a filing, scope shown. TDLR = estimated construction cost registered with the Texas Department of Licensing and Regulation, buildings only. Inc = investment committed in a local incentive agreement.

MW. IT = IT load. Gen = generation capacity. Design = planned capacity as the source states it, when the source does not say whether it is IT load or generation. The three are never added.

Online. Earliest known milestone (first power or completion). Basis: T = TDLR filing, C = company, R = county record, P = trade press or analyst. Dashes mean no public date.

Evidence. Signals present: state filing, local incentive record, air permit, named contractor, supply contract, confirmed groundbreaking. Confidence. High = primary document read. Medium = one primary source read secondhand, or two secondary. Low = single trade report or unverified.

Record only = listed in a county or state record; current build state not confirmed.

Three dollar figures per project, never added together

One bar per figure on one shared scale, 0 to $25B. A project can have one, two or three. Missing types are left out, not zeroed.

Sort by:

When each project builds and powers up

Bars run from groundbreaking to completion. Diamonds mark first power. Dashed means the date comes from press or a county record, not the company or a state filing. Letters at the end of a bar give the basis: T state filing, C company, R county, P press or analyst.

Scroll sideways to see every quarter.

Quarter
Stargate Abilene. Stargate Abilene: Partly operating. Groundbreaking 2022. Completion Dec 21, 2026.
Edged, Irving. Edged, Irving: Partly operating. Groundbreaking Jul 16, 2026. First power Jan 2025. Completion Mar 27, 2028.
STACK Infrastructure, Lancaster (DFW02). STACK Infrastructure, Lancaster (DFW02): Under construction. Groundbreaking May 21, 2025. First power 2026. Completion Dec 14, 2028.
QTS, Fort Worth. QTS, Fort Worth: Operating. Groundbreaking Jul 1, 2025. Completion Oct 1, 2027.
Skybox Datacenters, Hutto. Skybox Datacenters, Hutto: Under construction. Groundbreaking Oct 1, 2025. Completion Oct 30, 2028.
Google, Armstrong County (Crusoe Goodnight). Google, Armstrong County (Crusoe Goodnight): Under construction. Groundbreaking Oct 2025. Completion Jul 30, 2027.
Meta, El Paso. Meta, El Paso: Under construction. Groundbreaking Oct 2025. First power 2028. Completion Feb 28, 2029.
CloudBurst San Marcos GigaCenter. CloudBurst San Marcos GigaCenter: Under construction. Groundbreaking Nov 2025. First power Q4 2026.
Stargate Frontier, Shackelford County. Stargate Frontier, Shackelford County: Under construction. Groundbreaking Dec 2025. First power Q4 2026. Completion May 11, 2028.
Google Meitner Energy Center, Gray and Roberts Counties. Google Meitner Energy Center, Gray and Roberts Counties: Under construction. Groundbreaking Dec 19, 2025. Completion Apr 18, 2028.
Nexus Data Centers, Hubbard. Nexus Data Centers, Hubbard: Under construction. Groundbreaking Jan 6, 2026. First power Q4 2026. Completion Jan 5, 2028.
Galaxy Helios, Dickens County. Galaxy Helios, Dickens County: Under construction. Groundbreaking Mar 13, 2026. Completion Nov 29, 2027.
Crusoe Abilene, Microsoft campus. Crusoe Abilene, Microsoft campus: Under construction. Groundbreaking Mar 2026. First power 2027.
Poolside Project Horizon, Pecos County. Poolside Project Horizon, Pecos County: Paused. Groundbreaking Mar 2026. First power 2027.
Google, Haskell County. Google, Haskell County: Under construction. Groundbreaking Apr 1, 2026. First power Jun 2026. Completion Oct 27, 2027.
Riot Platforms, Corsicana. Riot Platforms, Corsicana: Operating. Groundbreaking Apr 27, 2026. Completion May 19, 2028.
Compass Datacenters, Red Oak. Compass Datacenters, Red Oak: Record only. Completion 2026.
IREN Childress. IREN Childress: Partly operating. First power 2026.
TeraWulf and Fluidstack, Abernathy. TeraWulf and Fluidstack, Abernathy: Under construction. First power 2026.
Amazon, Boling. Amazon, Boling: Announced. Groundbreaking Aug 1, 2026. Completion Sep 1, 2027.
Amazon, Floydada. Amazon, Floydada: Announced. Groundbreaking Aug 1, 2026. Completion Apr 1, 2027.
GW Ranch and Amazon, Pecos County. GW Ranch and Amazon, Pecos County: Announced. Groundbreaking Aug 1, 2026. First power 2027. Completion Dec 1, 2026.
Cipher Barber Lake, Mitchell County. Cipher Barber Lake, Mitchell County: Under construction. First power Q3 2026. Completion Jan 2027.
Switch, Round Rock. Switch, Round Rock: Partly operating. Groundbreaking Q3 2026. Completion Jun 1, 2028.
Stargate Milam County. Stargate Milam County: Under construction. First power Oct 2026. Completion Q4 2028.
Prometheus Hyperscale and Istmo, Reeves County. Prometheus Hyperscale and Istmo, Reeves County: Announced. First power 2027.
Texas Critical Data Centers, Odessa. Texas Critical Data Centers, Odessa: Announced. First power Q3 2027.
PowerBridge Alpha Digital Campus, Reeves County. PowerBridge Alpha Digital Campus, Reeves County: Announced. First power Q4 2027. Completion 2028.
Chevron and Microsoft, Project Kilby (Reeves County). Chevron and Microsoft, Project Kilby (Reeves County): Announced. First power 2028.
NRG and LandBridge, Reeves County (potential). NRG and LandBridge, Reeves County (potential): Announced. First power Q4 2029.

No public date yet: 7 projects. Nscale and Ionic, Ward County, Crusoe, Wilbarger County, Crusoe, Howard County (Elbow Creek), Compass Datacenters, Allen, Digital Realty, Dallas, Lancium, Fort Stockton, Oracle, Bexar County.

Dated before Q3 2026 and not drawn: Fermi America Project Matador, Carson County (groundbreaking Oct 2025, company statement); IREN Sweetwater, Nolan County (first power May 1, 2026, company statement); CoreWeave, Plano (completion Dec 31, 2023, trade press).

What is inside one

Poster of the interactive AI data hall exhibit: a cutaway of a data hall showing power and cooling paths

This tracker shows who is building where. To see what they are building, take apart our interactive AI data hall: the power path from the generators to every rack, the coolant path out to the cooling towers, and where AI fits in the control systems. The walk-through is in Anatomy of an AI data hall.

The Governor's audit asks for the fields this page already tracks

On August 3, 2026 the Governor directed the PUC and ERCOT to require each data center to disclose its incentives, projected electricity use and on-site generation, projected water use and sources, cooling technology and community impact measures. Source: the Governor's letter to PUC Chair Gleeson and ERCOT CEO Vegas. ERCOT's pause on energizing data centers of 75 MW or more and the December 10, 2026 report date are from ERCOT Board Item 14, September 14-15, 2026.

Audit fields in the Governor's August 3, 2026 letter against what this page tracks
Audit fieldWhere it appears hereProjects with a sourced valueProjects where it is not public
State and local tax incentives, grants, abatements or other public financial assistance received or expectedDollars column, Inc: program and amount where an agreement states one17 of 4225 of 42
Projected annual and peak electricity consumptionMW column (IT load, generation, design capacity). Capacity, not annual energy: no project states projected annual and peak consumption25 of 42 (capacity only)17 of 42
Progress on on-site electric generation, including generation typePower column and the generation-equipment role. Projects planning on-site gas, alone or with the grid14 of 42 (4 name a generation-equipment supplier)28 of 42
Projected annual and peak water consumption and anticipated water sourcesRecord, Water: source and cooling note where one is published6 of 42 (sources, not volumes)36 of 42
Cooling technologyNot a tracked field yet; cooling appears only in water notesnot trackedn/a
Community impact measuresNot a tracked field yetnot trackedn/a

The gaps are the point: this is what the public record shows today.

What you sell, and who is already buying it

Seven kinds of work are bought for these campuses. Open yours to see the named deals, then filter the table to the projects that carry them.

Midstream gas supply to campuses5 projects tagged

Firm gas transportation, last-mile laterals and, in the Permian, ethane as a second fuel.

Energy Transfer / Oracle. Gas supply agreements for three U.S. data centers, two in Texas; new lateral off the Hugh Brinson and North Texas pipelines under construction (Nov 2025).about 900,000 Mcf/dsec.gov
Energy Transfer / Crusoe, Abilene. Facilities to supply gas for the Abilene expansion; 14-mile lateral off Hugh Brinson completed; Hugh Brinson Phase I (1.5 Bcf/d) in full service by Sept 1, 2026.supports about 900 MWenergytransfer.comProjects: Crusoe Abilene, Microsoft campus
Energy Transfer / CloudBurst, San Marcos. Up to 450,000 MMBtu/d on the Oasis Pipeline for at least 10 years; subject to CloudBurst's final investment decision. Source is a trade search listing; Energy Transfer's own page returned 403.about 1.2 GW behind the metergasprocessingnews.comProjects: CloudBurst San Marcos GigaCenter
Energy Transfer / Nexus Hubbard. Firm transportation, initial volumes in Q4 2026.about 150 MMcf/d initialenergytransfer.comProjects: Nexus Data Centers, Hubbard
Istmo Midstream / Prometheus Hyperscale. Campus fueled by piped gas plus ethane from Istmo's co-located fractionation facility (trade report, Aug 21, 2026).up to 2.5 GWdatacenterdynamics.comProjects: Prometheus Hyperscale and Istmo, Reeves County

Selling gas supply or pipeline capacity to data center campuses? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Midstream gas: 5 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

On-site gas generation4 projects tagged

Turbines, reciprocating engines and packaged power, bought either by the plant owner who sells power or by the developer.

Chevron / Microsoft, Project Kilby. 20-year power agreement; majority GE Vernova turbines plus Solar Turbines (Caterpillar); FID expected by end-2026, first power 2028.about 2.67 GWchevron.comProjects: Chevron and Microsoft, Project Kilby (Reeves County)
VoltaGrid / Oracle. Modular gas generation for Oracle AI data centers using INNIO Jenbacher reciprocating engines and ABB, gas via Energy Transfer (Oct 2025).2.3 GWdatacenterdynamics.com
Enchanted Rock / El Paso Electric, for Meta. 813 modular gas generators of about 450 kW each; PUC approval pending, with judges recommending approval only with no cost pass-through to ratepayers (Sept 2026).366 MW, est. $499Minsideclimatenews.orgProjects: Meta, El Paso
Kodiak Gas Services. Six-year deal for baseload from about 40 gas reciprocating units for an unnamed West Texas data center; deployment Q4 2026 to Q1 2027.76 MW behind the meterdatacenterdynamics.com
Fermi America / Siemens Energy, Carson County. Six SGT-800 turbines financed through a $165M facility (delivery 2028) and three F-class units received.1.5 GW landed powersec.govProjects: Fermi America Project Matador, Carson County

Selling turbines, engines or packaged power to data center campuses? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged On-site generation: 4 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Electrical, medium-voltage and EPC3 projects tagged

Substations, transmission, medium-voltage work and multi-prime construction.

Mortenson, power-delivery EPC, Abilene. 200 MW / 138 kV substation (2022-24); 12.5-acre, 1 GW, 345 kV greenfield substation with five main power transformers energized by March 10, 2026.1 GW substationmortenson.comProjects: Stargate Abilene
DPR Construction, Rosendin, Southland Industries. General contractor, electrical and mechanical on Crusoe's Abilene and Armstrong County campuses; multi-prime reporting to the owner.4,000+ craft workers across both sites at peaknewenglandconstruction.newsProjects: Stargate Abilene; Google, Armstrong County (Crusoe Goodnight)
Primoris and TSK, Project Matador. Primoris selected for balance of plant and TSK for engineering of the SGT6-5000F units.power islandsec.govProjects: Fermi America Project Matador, Carson County

Selling substation, medium-voltage or EPC work to data center campuses? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Electrical and EPC: 3 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Water sourcing and treatment3 projects tagged

Make-up water, brackish groundwater, treated produced water and cooling-water technology.

Texas Pacific Land / Chevron, Reeves County. Exclusive right to source aquifer-derived brackish water for the Kilby plant; Chevron says it will use non-potable brackish groundwater.Kilby planttexaspacific.comProjects: Chevron and Microsoft, Project Kilby (Reeves County)
Texas Pacific Land, Orla produced-water plant. Desalination plant construction complete and commissioning started; not tied to a named data center.10,000 bbl/day initial; $55.8M spent through June 30, 2026sec.gov
Amazon, Pecos County. Will use water not suitable for drinking or irrigation, low-water cooling, and says it will explore beneficial use of produced water (company statement, Aug 2026).campusdatacenterdynamics.comProjects: GW Ranch and Amazon, Pecos County
AirJoule / Nexus Hubbard. Proposed water purchase agreement to harvest water from waste heat; deployment 2H 2026 (trade report).proposeddatacenterdynamics.comProjects: Nexus Data Centers, Hubbard

Selling water supply or treatment to data center campuses? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Water: 3 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Land, surface rights and mineral owners4 projects tagged

Powered land, surface rights and option leases near the Waha gas hub.

Texas Pacific Land / Chevron. Land sold for $42.5M (nominal cash at closing, annual payments through 2046) plus water rights.$42.5Msec.govProjects: Chevron and Microsoft, Project Kilby (Reeves County)
Texas Pacific Land, Shackelford and Jones Counties. Land buys 'in connection with our data center and power generation initiatives', part of $110.2M acquired in the first half of 2026 that also included Winkler County.part of $110.2Msec.gov
LandBridge / PowerBridge. Option to lease about 3,400 acres in Reeves County for the 2 GW Alpha Digital Campus; not a firm lease and subject to entitlements.about 3,400 acresdatacenterdynamics.comProjects: PowerBridge Alpha Digital Campus, Reeves County
LandBridge / NRG. Strategic agreement on a potential Reeves County site for a gas plant serving a data center; air permit and interconnection requests filed.1,100 MWs206.q4cdn.comProjects: NRG and LandBridge, Reeves County (potential)
Longfellow Ranch / Poolside. 568 acres in Pecos County for Project Horizon, which later lost its anchor tenant.568 acresdatacenterdynamics.comProjects: Poolside Project Horizon, Pecos County

Offering land or surface rights to data center developers? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Land: 4 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Site preparation and civil0 projects tagged

Land clearing, grading and civil work.

No sourced deal found yet. See the gap note.

Selling site prep or civil work to data center campuses? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Site prep: 0 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Oilfield-services and compression pivots1 project tagged

Oilfield-services and compression companies selling power as a new line of business.

Liberty Energy. Up to 1 GW with Vantage Data Centers over five years; 330 MW reservation with an undisclosed Texas developer; JV with PowerBridge on the 2 GW Alpha Digital Campus (Jul 22, 2026); alliance with SLB for modular infrastructure plus power (Jul 14, 2026).up to 1 GW with Vantageinvestors.libertyenergy.comProjects: PowerBridge Alpha Digital Campus, Reeves County
Kodiak Gas Services. Contract compression company with a 76 MW behind-the-meter deal; acquired Distributed Power Solutions (now Kodiak Power Solutions); targets 2 GW of power by 2030.76 MWdatacenterdynamics.com
Solaris Energy Infrastructure. Power generation about 76% of segment adjusted EBITDA in Q1 2026; firm equipment orders for a fleet of about 3,100 MW by end-2029; three data-center agreements whose sites are not identified in the filing.about 3,100 MW fleet by end-2029sec.gov

Taking oilfield-services or compression capacity into data center power? ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

Book a 30-minute call

Tracked projects tagged Oilfield pivots: 1 of 42, as of Oct 9, 2026. 30 minutes, no obligation either way.

Companies on more than one project

CompanyRolesProjectsProject links
Operator6Stargate Abilene; Crusoe Abilene, Microsoft campus; Google, Armstrong County (Crusoe Goodnight); Stargate Abilene expansion (+600 MW); Crusoe, Wilbarger County; Crusoe, Howard County (Elbow Creek)
Design firm5Stargate Milam County; Skybox Datacenters, Hutto; QTS, Fort Worth; STACK Infrastructure, Lancaster (DFW02); Switch, Round Rock
Tenant, Operator4Crusoe Abilene, Microsoft campus; Chevron and Microsoft, Project Kilby (Reeves County); IREN Childress; Nscale and Ionic, Ward County
Operator, Tenant3GW Ranch and Amazon, Pecos County; Amazon, Floydada; Amazon, Boling
Gas supply3Crusoe Abilene, Microsoft campus; CloudBurst San Marcos GigaCenter; Nexus Data Centers, Hubbard
Design firm3GW Ranch and Amazon, Pecos County; Amazon, Floydada; Amazon, Boling
Tenant, Operator3Google, Armstrong County (Crusoe Goodnight); Google, Haskell County; Google Meitner Energy Center, Gray and Roberts Counties
Design firm3Google, Haskell County; Google Meitner Energy Center, Gray and Roberts Counties; Nexus Data Centers, Hubbard
Tenant3Stargate Abilene; Stargate Frontier, Shackelford County; Stargate Milam County
Tenant, Operator3Stargate Abilene; Stargate Frontier, Shackelford County; Oracle, Bexar County
Operator2Compass Datacenters, Red Oak; Compass Datacenters, Allen
Tenant, Operator2Galaxy Helios, Dickens County; CoreWeave, Plano
General contractor2Stargate Abilene; Google, Armstrong County (Crusoe Goodnight)
Tenant, Operator2Cipher Barber Lake, Mitchell County; TeraWulf and Fluidstack, Abernathy
Design firm2Stargate Abilene; Google, Armstrong County (Crusoe Goodnight)
Operator2IREN Sweetwater, Nolan County; IREN Childress
Developer, Operator2Stargate Abilene; Lancium, Fort Stockton
Land, Developer2PowerBridge Alpha Digital Campus, Reeves County; NRG and LandBridge, Reeves County (potential)
Electrical2Stargate Abilene; Google, Armstrong County (Crusoe Goodnight)
Mechanical2Stargate Abilene; Google, Armstrong County (Crusoe Goodnight)
Design firm2Meta, El Paso; Galaxy Helios, Dickens County

47 more state filings we have not confirmed as projects

These are Texas Department of Licensing and Regulation filings for data centers that do not match any project above. Registered cost is the filer's estimate for buildings. $24.2B total, listed separately and never added to the projects above. A filing becomes a project here only after a second source (company, county or utility) confirms it.

47 TDLR filings not confirmed as projects. Source: TDLR TABS, data as of Oct 9, 2026.
Filing Owner of recordWhereRegistered costBuildings (registrations)Start to completionDesign firmPossible match
txf-2027000835
Childress DC3, LLCProject Hyper - Childress
Childress, Childress County525 C CO RD 23$2.4B12026-10-05 to 2028-05-31HKS, Inc.Press (DCD, Baxtel) ties 'Project Hyper' to Crusoe and Lancium's 1.4 GW Childress campus (three buildings at $2.4B each). Not promoted: a second source is needed.TDLR
txf-2027000830
Childress DC2, LLCProject Hyper - Childress
Childress, Childress County525 B CO RD 23$2.4B12026-09-01 to 2028-04-28HKS, Inc.Press (DCD, Baxtel) ties 'Project Hyper' to Crusoe and Lancium's 1.4 GW Childress campus (three buildings at $2.4B each). Not promoted: a second source is needed.TDLR
txf-2027000824
Childress DC1, LLCProject Hyper - Childress
Childress, Childress County525 A CO RD 23$2.4B12026-07-06 to 2028-02-28HKS, Inc.Press (DCD, Baxtel) ties 'Project Hyper' to Crusoe and Lancium's 1.4 GW Childress campus (three buildings at $2.4B each). Not promoted: a second source is needed.TDLR
txf-2026008169
DB Data Center Red Oak, LLCDataBank Red Oak - DFW11 TFO; DataBank Red Oak - DFW14 Base Building; DataBank Red Oak - DFW15 Base Building; Databank R
Red Oak, Ellis CountyStainback Rd$1.89B62025-02-01 to 2029-07-31JHET Architects, PLLCNone found.TDLR
txf-2025016366
QTS Dallas I, LLCQTS DFW2 DC2; QTS DFW2 DC3; QTS DFW2-DC5; QTS DFW2-DC6
Wilmer, Dallas County303 Mason Road$1.23B42025-05-01 to 2027-09-01Corgan Associates, Inc.; Highland AssociatesNone found.TDLR
txf-2026026121
Rowan Digital InfrastructureAUS02
Temple, Bell County1855 Bob White Road$780M12026-08-28 to 2027-08-27Not listedNone found.TDLR
txf-2025012765
Microsoft CorporationSAT89/90 Data Center
Castroville, Medina County2995 US HWY 90 W$765M12025-06-01 to 2027-07-31WSP USANone found.TDLR
txf-2025012185
MicrosoftMicrosoft SAT93; Microsoft SAT94; SAT93; SAT94
Medina, Medina CountyCounty Road 381$752M42025-05-13 to 2029-05-31Gensler Architecture, Design & Planning, P.C.None found.TDLR
txf-2026001234
VANTAGE DATA CENTERS TX1 LLCTX12 TFO; VANTAGE DATA CENTER (TX12)
San Antonio, Bexar County17420 Omicron Dr$725M22025-10-14 to 2028-03-30Jacobs; Sheehan Nagle Hartray ArchitectsNone found.TDLR
txf-2025019833
Homebound Group LLCData Center THM1A; Data Center THM2A
Haskell, Haskell County10357 Loop Road$700M22025-06-18 to 2028-03-15HDR Engineering Inc.; HDR Engineering, Inc.Google, Haskell County. Same owner (Homebound Group LLC, Google-linked per DCD) as the Haskell project; this second site (THM1A/2A, 10357 Loop Rd) is not part of it.TDLR
txf-2025016916
DatabankDatabank Red Oak - DFW11; Databank Red Oak - DFW12
Red Oak, Ellis CountyStainback Rd$650M22025-12-15 to 2028-11-15JHET ArchitectsNone found.TDLR
txf-2025010445
Lancaster Data Center Campus, LPSkybox - LAN01 - Fit Out; Skybox - LAN01 - Fit Out D2B; Skybox - Lancaster 1 Initial Improvements
Lancaster, Dallas County2401 South Dallas Ave.$649M32025-03-01 to 2027-04-01Corgan; Corgan Associates, Inc.; Corgan AsssociatesNone found.TDLR
txf-2026016944
QTS Dallas I, LLCQTS DFW2-DC7
Lancaster, Dallas County1341 Sunrise Rd.$580M22026-09-01 to 2027-12-01Corgan Associates; Corgan Associates Inc.None found.TDLR
txf-2026025297
Platon Investments LLCRise 2A
Vernon, Wilbarger CountyFM 2897 S$500M12026-03-31 to 2028-03-31Kimberly - HornPress (DCD) says Planton / Platon Investments LLC is Google (Googleplex mailing address); Project Rise in Vernon is not Crusoe's Wilbarger site.TDLR
txf-2026025053
Planton Investments LLCProject Rise 1A
Vernon, Wilbarger CountyFM 2897 S$500M12026-03-31 to 2028-03-31Kimberly - HornPress (DCD) says Planton / Platon Investments LLC is Google (Googleplex mailing address); Project Rise in Vernon is not Crusoe's Wilbarger site.TDLR
txf-2026007415
Sharka LLCSharka Data Center - Building 5
Midlothian, Ellis County3411 Railport Parkway$492M12026-01-28 to 2027-02-24Not listedNone found.TDLR
txf-2027003019
Soluna KK Energy Service Co LLCProject Kati II
Unknown, Willacy County1392 FM 1420 Santa Monica$472M12026-10-08 to 2027-10-08HKS, Inc.Project Kati II, Willacy County; relationship to listed projects: none known.TDLR
txf-2027001701
AIL INVESTMENT LPColovore Alliance
Fort Worth, Denton County14700 Heritage Parkway$430M12026-12-01 to 2028-12-01Ci DesignNone found.TDLR
txf-2026023621
ALIGNED DATA CENTERS (ABERNATHY) PROPCO, LLCADC - LBB01
Abernathy, Hale County1421 FM 54$425M12026-04-24 to 2027-11-15CORGANTeraWulf and Fluidstack, Abernathy. Aligned Data Centers (Abernathy) PropCo is in the same town as the TeraWulf and Fluidstack project; the relationship is unverified.TDLR
txf-2026008231
MicrosoftMicrosoft SAT82 Data Center
Castroville, Medina County3580 FM 471 N$400M12026-08-13 to 2028-07-24Not listedNone found.TDLR
txf-2026019473
Lockhart Property, LLCPrime Data Center AUS-01
Lockhart, Caldwell County1395 Bob White Road$400M12026-06-01 to 2027-09-30GenslerNone found.TDLR
txf-2027000611
Beacon Point DC LLC aka Lon Hill Infrastructure LLCBeacon Point Data Center Project
Corpus Christi, Nueces County4650 FM 1694, ROBSTOWN, TX 78380$399M12026-09-28 to 2027-11-05Jacobs Project Management Co.None found.TDLR
txf-2026023619
Giga AFM LLCBT Gateway Data Center
Royse City, Hunt County4989 COUNTY ROAD 2656, ROYSE CITY TX 75189$384M12026-08-01 to 2027-02-12Not listedNone found.TDLR
txf-2027002962
Roger Donald WallaceProject Longhorn - Building One
Cedar Creek, Bastrop CountyEarl Callahan Rd. near Walter Hoffman Road$366M12026-11-30 to 2028-01-31GenslerOwner of record is an individual; Gensler design.TDLR
txf-2025013563
Digital RealtyDigital Garland Campus; Digital Realty DFW37 Suite 105/205; Project Gold Phase 2 - DFW 39; Project Gold Phase 2 - DFW39
Garland, Dallas County1512 Ferris Road$331M52025-05-01 to 2027-10-29HED; JHET Architects; The M Group ArchitectsNone found.TDLR
txf-2027000488
Digital Garland 2C, L.P.Digital Garland Campus
Garland, Dallas County1602 Ferris Road$300M12026-06-01 to 2029-01-01HEDNone found.TDLR
txf-2026001400
SDC DFWC, LPStream Data Centers - DFWC1
Wilmer, Dallas County930 N Sunrise Rd$300M12026-04-01 to 2027-10-27Gensler Architecture, Design and Planning P.C.None found.TDLR
txf-2027000200
Colovore Austin 1, LLCColovore Hutto
Hutto, Williamson County2401 Innovation Boulevard$280M12026-12-01 to 2028-12-01Ci DesignNone found.TDLR
txf-2026001239
CyrusOneCyrusOne DFW10 | Tenant Fit Out
Whitney, Hill County557 CR 3610$275M12026-05-23 to 2026-10-06JHET ArchitectsNone found.TDLR
txf-2026003003
Retained Vantage Data Centers DevelopmentVantage Data Centers TX22
San Antonio, Bexar County5207 Rogers Road$272M12025-10-22 to 2027-06-15CorganNone found.TDLR
txf-2025015383
Aligned Data CentersDFW04 TFO; DFW04-2
Plano, Collin County601 North Star Rd.$240M22025-06-01 to 2026-12-31CorganNone found.TDLR
txf-2026008019
Polmer LLCTemple Data Center
Temple, Bell County2230 Eberhardt Rd$197M12025-12-15 to 2026-09-30Not listedNone found.TDLR
txf-2025021441
QTS Dallas I, LLCQTS DFW2-DC4
Dallas, Dallas County794 W Beltline Road$175M12025-11-15 to 2027-05-01Corgan Associates, Inc.None found.TDLR
txf-2026018081
DB Data Center Red Oak 12, LLCDataBank Red Oak - DFW12 TFO
Red Oak, Ellis CountyStainback Rd$155M12026-05-08 to 2027-10-30JHET Architects, PLLCNone found.TDLR
txf-2026014266
Digital Garland 2B, L.P.Digital Garland Campus
Garland, Dallas County1512 Ferris Road$140M12026-05-06 to 2027-06-10HEDNone found.TDLR
txf-2026006358
VANTAGE DATA CENTERS TX2 LLCVantage Data Centers TX21 Tenant Fit-out
San Antonio, Bexar County5207 ROGERS ROAD$135M12025-12-01 to 2026-06-02CorganNone found.TDLR
txf-2025026552
Digital RealtyProject Gold Phase 2 - DFW44; Project Gold Phase 2 DFW44
Lewisville, Denton County2501 Edmonds LN$120M32025-09-01 to 2027-10-29M Group Architects; The M Group ArchitectsNone found.TDLR
txf-2026008433
Vantage Data Centers TX11TX11 OPEL Fit-Up
San Antonio, Bexar County14720 Omicron Dr$95M12026-01-07 to 2026-06-12Sheehan Nagle Hartray ArchitectsNone found.TDLR
txf-2027002672
Circle T Owner LPDAL130 - Data Center
Westlake, Tarrant County13572 N. Main Street$83M12026-12-01 to 2027-06-01Ci DesignNone found.TDLR
txf-2026003158
Sabey Data CentersSabey Austin Building B: DH B35; Sabey Austin Building B: DH B36
Round Rock, Williamson County1300 Louis Henna Blvd.$80M22025-11-01 to 2026-09-01CorganNone found.TDLR
txf-2026016734
Prairie Ridge Phase 1 Owner LPAREP Power House Grand Prairie
Midlothian, Ellis County881 Miller Road$73M12026-04-01 to 2028-04-01Ci ArchitectsNone found.TDLR
txf-2026007843
Digital RealityDigital Reality DFW37 Suite 110/210
Garland, Dallas County1502 Ferris Road$60M12026-06-01 to 2027-02-28JHET Architects, PLLCNone found.TDLR
txf-2026008115
1515 Roundtable Dr Property LLCPrime DC 3MW Buildout
Dallas, Dallas County1455 Round Table Dr.$48M12025-12-01 to 2026-06-01AO ArchitectsNone found.TDLR
txf-2025013924
American Real Estate PartnersAREP Powerhouse Las Colinas
Irving, Dallas County111 Customer Way$47M12025-09-23 to 2026-08-14HKS Inc.None found.TDLR
txf-2025015318
Oppidan5MW Temple Data Center
Temple, Bell County2313 Eberhardt Road$31M12025-07-14 to 2026-10-16Salas O'BrienNone found.TDLR
txf-2025025376
MapletreeEvocative DAL6 Infrastructure Upgrades
Plano, Collin County1221 Coit Road$30M12025-09-05 to 2027-02-27Burns EngineeringNone found.TDLR
txf-2026022947
Data Center Houston, LLCHOU2 CAPACITY EXPANSION
Houston, Harris County5170 WESTWAY PARK BLVD$20M12026-07-07 to 2027-09-27CORGANNone found.TDLR
Source: TDLR TABS. Locations are county-level until geocoded.

How this is built

Public records only. For each project we chain the named operator to the granting government, then the appraisal district or reinvestment zone, then the Chapter 380, 381 or 312 incentive, then read the status. Megawatts never appear in the incentive record, so each MW figure comes from an external source with a confidence band.

Texas SB 6 restricts what utilities may disclose about named large-load customers, so where a figure is not public we show “not published” rather than an estimate.

The three dollar figures

  • TDLR estimate: the registrant's estimate of construction cost for accessibility review, buildings only. It is often shell only or fit-out only, and it excludes power plants, substations and GPUs. A campus appears as many registrations; we sum them, and shell and fit-out registrations can overlap.
  • Announced: from a company release, SEC filing or trade report, with its scope named. Statewide pledges (for example Google's $40B for Texas through 2027) are never assigned to a site.
  • Incentive-committed: the investment a company committed to in a local agreement, where the text states it.

Source ranking and confidence

  • Source order: primary filing, then county record, then company release, then trade press. Trackers are used only to discover names, never cited.
  • Confidence: High = a primary document was read. Medium = one primary source read secondhand, or two secondary. Low = a single trade report or unverified.
  • Evidence is the count of six observable signals present: a state filing, a local incentive record, an air permit, a named contractor, a supply contract, a confirmed groundbreaking. It replaces the old BUILD/CAUTION verdict, which separated 1 project of 16.
  • A role marked “Not publicly named (checked Oct 9, 2026)” means we looked and found none. “Not yet checked” means the project has not been through that pass.

Monthly refresh

Each month we re-search TDLR by owner entity, check county and city agendas and the Comptroller incentive records, re-pull company filings and release pages, re-run the trap checks (shell against fit-out double counting, statewide pledges, cancelled projects), then log every change below with its date. A refresh also runs once after ERCOT's December 10 report.

Compiled by ModalPoint. Corrections: send a correction.

Quote or cite any figure with a link to this page. To show the map on your site, use the embed code under the map.

Cite this page: ModalPoint, “Texas Data Center Map,” updated Oct 9, 2026, modalpoint.com/texas-data-center-map

Questions about Texas data centers

How many data centers are being built in Texas?

We track 42 projects, 25 of them building or running as of Oct 9, 2026. That is a tracked list, not a census. The Governor's August 3, 2026 letter puts the ERCOT connection queue at approximately 474 gigawatts of requested large load, about 90 percent of it data centers, which is far more than will be built.

Who is building data centers in Texas?

Operators with the most projects on this list: Crusoe (6 projects), Amazon Data Services (3 projects), Compass Datacenters (2 projects) and IREN (2 projects). Tenants and customers include Oracle and OpenAI, Microsoft, Google, Meta and Amazon. Each record names the operator, tenant and legal entity.

Where are the biggest data center projects in Texas?

By disclosed scale: Stargate Frontier (Shackelford County, $25B campus), Stargate Abilene (Taylor County, $15B JV financing) and CloudBurst San Marcos GigaCenter (Hays County, $14.5B campus). The scopes differ, so the figures are not comparable one for one. By count of projects, the leading regions are West Texas 10, Permian Basin 10 and North Texas 8.

How much are companies spending on Texas data centers?

Three different figures are published and they are not additive: announced investment (13 projects, largest Stargate Frontier at $25B for the campus), state-filed construction cost (19 projects, $35.9B registered, buildings only), and local incentive commitments (8 projects with a figure). Scope varies from full campus to power plant only.

Do data centers have their own power plants?

Some do. 14 of 21 projects with a sourced power source plan on-site gas generation, alone or with the grid. Example: Chevron and Microsoft plan about 2.67 GW of generation for a Reeves County campus, first power in 2028. Others buy power from the ERCOT grid.

What is the ERCOT pause on new data centers?

On August 3, 2026 the Governor directed regulators to audit data centers advancing through the grid queue. ERCOT paused approvals to energize data centers of 75 MW or more until it files its verification report, due December 10, 2026. Developers of off-grid campuses say the pause does not reach them.

How much power do Texas data centers use?

Planned loads run from tens of megawatts to over a gigawatt per campus. We show IT load, generation and design capacity separately and never add them; a figure is blank when no source states it.

Which Texas counties have the most data center projects?

Reeves County (4), Dallas County (3), Pecos County (3) and Taylor County (3). Counties with the most announced power are not always the ones with the most projects.

How often is this updated, and where does the data come from?

Monthly, plus once after ERCOT's December 10 report. Sources are state filings (TDLR), county and city agreements, the Texas Comptroller incentive database, SEC filings, company releases, and trade press, ranked in that order. See How this is built.

How do I sell to Texas data center projects?

Start with who buys what you sell: gas supply, on-site generation, electrical and EPC work, water, land, site prep. The seller view lists named deals per segment and the contractors, suppliers and developers on each project. See What you sell, and who is already buying it.

Selling into data centers? We map the buyers and help you win the work.

On every project above, someone decides what gets bought: a developer, a general contractor, a power EPC or a plant owner. ModalPoint helps you win that business with buyer mapping, positioning and a go-to-market plan.

42 projects tracked, 25 building or running. Data as of Oct 9, 2026.